75-20-231: Expedited review.
Where this section sits in the code
- TITLE 75. ENVIRONMENTAL PROTECTION
- CHAPTER 20. MAJOR FACILITY SITING
- Part 2. Certification Proceedings
(1) Except as provided in 75-1-208(4)(b), the department shall issue a certification decision within 90 days from the date on which an application is considered complete for a facility that:
(a) is unlikely to result in significant adverse environmental impacts based on the criteria listed in 75-20-232; or
(b) is presently in existence and proposed for upgrade, reconstruction, or relocation and is unlikely to result in significant impacts pursuant to 75-20-232.
(2) A facility that qualifies for expedited review is exempt from undergoing an alternative siting study, except as provided in 75-1-201.