N.D. Cent. Code § 24-02-25.2: Actions against contractor and surety - Time
Where this section sits in the code
- Title 24 Highways, Bridges, And Ferries
- Chapter 24-02 Director Of The Department Of Transportation
Any person who has furnished labor, materials, or supplies and made a claim under section 24-02-25.1 has the right to commence an action to recover the amount of the person's claim against the contractor or surety within one year of the date of the final acceptance of the project by the department.
Collected 2026-09-02T21:04:14Z. Source file · JSON