N.D. Cent. Code § 35-27-14: Lien not lost for failure to file within time - Exception

Read at publisher ↗
Where this section sits in the code
  1. Title 35 Liens
  2. Chapter 35-27 Construction Lien

A failure to file within ninety days does not defeat the lien except as against purchasers or encumbrancers in good faith and for value whose rights accrue before the lien is filed, and as against the owner to the extent of the amount paid to a contractor before the recording of the lien. A lien may not be filed more than three years after the date of the first item of material is furnished.

Collected 2026-09-02T21:04:14Z. Source file · JSON