N.D. Cent. Code § 35-27-22: Order of priority of classes of construction liens

Read at publisher ↗
Where this section sits in the code
  1. Title 35 Liens
  2. Chapter 35-27 Construction Lien

1.Liens perfected under this chapter have priority in the following order:

a.For manual labor.

b.For materials.

c.Subcontractors other than manual laborers.

d.Original contractors.

2.Liens for manual labor filed within the ninety-day period must share ratably in the security. Liens for manual labor filed after the ninety-day period have priority in the order of the filing of such liens. Liens for materials filed within the ninety-day period must share ratably in the security and liens filed after the ninety-day period have priority in the order of the filing of such liens.