N.D. Cent. Code § 35-27-22: Order of priority of classes of construction liens
Where this section sits in the code
- Title 35 Liens
- Chapter 35-27 Construction Lien
1.Liens perfected under this chapter have priority in the following order:
a.For manual labor.
b.For materials.
c.Subcontractors other than manual laborers.
d.Original contractors.
2.Liens for manual labor filed within the ninety-day period must share ratably in the security. Liens for manual labor filed after the ninety-day period have priority in the order of the filing of such liens. Liens for materials filed within the ninety-day period must share ratably in the security and liens filed after the ninety-day period have priority in the order of the filing of such liens.
Collected 2026-09-02T21:04:14Z. Source file · JSON