N.D. Cent. Code § 61-02-14.3: Commission agreements - Terms, conditions, and reapplication

Read at publisher ↗
Where this section sits in the code
  1. Title 61 Waters
  2. Chapter 61-02 Water Commission

An agreement for funding which is approved by the commission to fund a water project under this chapter must require a progress report to the commission at least every four years if the term of the project exceeds four years. If a progress report is not timely received or, if after a review of a progress report, the commission determines the project has not made sufficient progress, the commission may terminate the agreement for project funding. The project sponsor may submit a new application to the commission for funding for a project for which the commission previously terminated funding.