Neb. Rev. Stat. § 73-1117: Contracts; changes authorized.
Where this section sits in the code
- Chapter 73 - PUBLIC LETTINGS AND CONTRACTS
A design-build contract and a construction manager-general contractor contract may be conditioned upon later refinements in scope and price and may permit an authorized agency in agreement with the design-builder or construction manager to make changes in the project without invalidating the contract.
Collected 2026-10-18T06:04:00Z. Source file · JSON