N.J. Stat. § 48:3-87.2f: Eligible qualified offshore wind project, retain, incremental federal tax benefits, report.
Where this section sits in the code
- TITLE 48 PUBLIC UTILITIES
6. No later than one year after the date of enactment of P.L.2023, c.99 (C.48:3-87.2a et seq.), an eligible qualified offshore wind project that elects to retain incremental federal tax benefits pursuant to section 3 of P.L.2023, c.99 (C.48:3-87.2c) shall submit to the board a report on the anticipated environmental impacts of the project, the anticipated economic benefits of the project, the financial viability of the project, and the feasibility of completing the project by the commercial operation date approved by the board, including any extensions thereto.
L.2023, c.99, s.6.