N.J. Stat. § 48:7-35: Approval of certificate of public convenience and necessity application, other circumstances, post-notice, hearing.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 48 PUBLIC UTILITIES

6. a. The Board of Public Utilities shall, after notice and hearing, approve an electric public utility’s application for a certificate of public convenience and necessity submitted pursuant to section 4 of P.L.2026, c.34 (C.48:7-33) that has not been approved pursuant to section 5 of P.L.2026, c.34 (C.48:7-34) if the board finds that:

(1) the supplemental project is necessary to provide safe, adequate, and reliable service to the utility’s customers and is a reasonable and cost-effective means of satisfying those service needs;

(2) the utility can efficiently manage and supervise the construction process and has taken sufficient action to ensure adequate and efficient construction and supervision of the construction; and

(3) the utility can finance the proposed construction without significant adverse financial consequences for the utility or its customers .

b. In determining whether the project is a reasonable and cost-effective means of meeting the requirements of paragraph (1) of subsection a. of this section, the board shall consider whether, and to what extent, the project:

(1) reduces energy and capacity prices for customers in the State, including the potential to reduce future price increases or price volatility;

(2) enhances the reliability and resilience of the utility’s transmission or distribution system;

(3) facilitates the connection of new load or generation resources to the electric grid;

(4) provides benefits to customers in the State, including, but not limited to, reduced line losses, reduced curtailment of energy generation resources, and reduced transmission congestion; and

(5) is supported by the preponderance of the evidence in the utility’s justification submitted pursuant to paragraph (3) of subsection a. of section 4 of P.L.2026, c.34 (C.48:7-33) for any decision not to deploy ATTs.

c. The board shall issue an order with its determination regarding an application for a certificate submitted pursuant to section 4 of P.L.2026, c.34 (C.48:7-33) and reviewed under this section no later than 180 days after the submission of a completed application. The board may extend this period by an additional period not to exceed 90 days. The board may condition its approval of a certificate under this section on changes to the utility’s application that the board deems to be in the public interest.

d. The board shall confine its review of a supplemental project under this section to the enumerated criteria in subsections a. and b. of this section. Nothing in this section shall authorize the board to conduct a siting review of the project. The board shall not consider the environmental impacts of the project in the board’s determination under this section.

L.2026, c.34, s.6.