NRS 338.1691: Qualifications for construction manager at risk.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 28 — PUBLIC WORKS AND PLANNING
  2. CHAPTER 338 - PUBLIC WORKS
  3. CONTRACTS INVOLVING CONSTRUCTION MANAGERS AT RISK

To qualify to enter into contracts with a public body for preconstruction services and to construct a public work, a construction manager at risk must:

1. Not have been found liable for breach of contract with respect to a previous project, other than a breach for legitimate cause, during the 5 years immediately preceding the date of the advertisement for proposals pursuant to NRS 338.1692;

2. Not have been disqualified from being awarded a contract pursuant to NRS 338.017, 338.13895, 338.1475 or 408.333;

3. Not have entered into a contract with a public body to act as a construction manager as agent during the 4 years immediately preceding the date of the advertisement for proposals pursuant to NRS 338.1692;

4. Be licensed as a contractor pursuant to chapter 624 of NRS; and

5. If the project is for the construction of a public work of the State, be qualified to bid on a public work of the State pursuant to NRS 338.1379.