NRS 338.535: Public body to provide notice concerning progress payments and retainage payments to certain subcontractors and suppliers.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 28 — PUBLIC WORKS AND PLANNING
  2. CHAPTER 338 - PUBLIC WORKS
  3. PROGRESS PAYMENTS
  4. Payments Made by Contractor to Subcontractors and Suppliers

Within 5 working days after a public body receives a written request from a subcontractor or supplier of the contractor with respect to a contract which has not been fully performed, the public body shall notify the subcontractor or supplier in writing of the following:

1. The date the public body made a specified progress payment or retainage payment to a contractor;

2. Whether the public body has paid the entire amount of a specified progress payment or retainage payment to the contractor; and

3. The amount withheld by the public body from a specified progress payment or retainage payment to the contractor, if any.