NRS 704.79886: Commission to require transmission providers to join regional transmission organization; waiver or delay of requirement.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 58 — ENERGY; PUBLIC UTILITIES AND SIMILAR ENTITIES
  2. CHAPTER 704 - REGULATION OF PUBLIC UTILITIES GENERALLY
  3. ELECTRIC SERVICE
  4. Regional Transmission Coordination

1. Except as otherwise provided in subsection 2, the Commission shall require every transmission provider in this State to join a regional transmission organization on or before January 1, 2030.

2. Upon application by a transmission provider, the Commission may waive or delay the requirement in subsection 1 if:

(a) The transmission provider files an application with the Commission on or before January 1, 2027, requesting the waiver or delay;

(b) The transmission provider demonstrates:

(1) That the transmission provider has made all reasonable efforts to comply with the requirement but is unable to find a viable and available regional transmission organization that the transmission provider can join on or before January 1, 2030; or

(2) That it would not be in the best interests of the transmission provider and its customers to join a regional transmission organization on or before January 1, 2030; and

(c) The Commission determines that it is in the public interest to grant the requested waiver or delay.

Collected 2026-09-03T05:51:47Z. Source file · JSON