NRS 704.873: Commission has exclusive jurisdiction to determine need for utility facilities of certain public utilities; other permitting entities precluded from considering need.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 58 — ENERGY; PUBLIC UTILITIES AND SIMILAR ENTITIES
  2. CHAPTER 704 - REGULATION OF PUBLIC UTILITIES GENERALLY
  3. CONSTRUCTION OF UTILITY FACILITIES: UTILITY ENVIRONMENTAL PROTECTION ACT

If a public utility that is subject to the provisions of NRS 704.736 to 704.754, inclusive, applies to the Commission for a permit for the construction of a utility facility:

1. The Commission has exclusive jurisdiction with regard to the determination of whether a need exists for the utility facility; and

2. No other permitting entity may consider, in its review of any application for a permit, license or other approval for the construction of the utility facility, whether a need exists for the utility facility.