N.Y.C. Admin. Code § 28-104.2.7: § 28-104.2.7 Time period for review.

Read at publisher ↗
Where this section sits in the code
  1. New York City Administrative Code
  2. Title 28
  3. Chapter 1: Administration

Completed construction documents complying with the provisions of this code and other applicable laws and rules shall be approved by the commissioner and written notice of approval shall be given the applicant promptly and no later than 40 calendar days after the submission of a complete application.

Exceptions:

1. On or before the fortieth day, the commissioner may, for good cause shown and upon notification to the applicant, extend such time for an additional 20 calendar days.

2. Such time period for review shall commence in accordance with article 107 for single room occupancy multiple dwellings.