A. A public construction contract shall provide for partial

payment based upon work completed. The contract shall provide that

up to five percent (5%) of all partial payments made shall be

withheld as retainage until the project is fifty percent (50%)

complete as determined by the awarding agency. When the awarding

public agency determines that the project is at least fifty percent

(50%) complete, the retainage amount shall be two and one-half

percent (2.5%) with respect to the balance of the work.

B. The Department of Transportation or the Oklahoma Turnpike

Authority shall not withhold retainage on public construction

contracts awarded by the Department or the Authority.

C. The Department of Transportation shall not withhold

retainage or require any bond on projects awarded to railroads on

the railroad's privately owned or operated rail property.