ORS 279C.315: Waiver of damages for unreasonable delay by contracting agency against public policy.

Read at publisher ↗
Where this section sits in the code
  1. 07 - Public Facilities and Finance
  2. 26. Public Facilities, Contracting and insurance
  3. Chapter 279C — Public Contracting - Public Improvements and Related Contracts

(1) Any clause in a public improvement contract that purports to waive, release or extinguish the rights of a contractor to damages or an equitable adjustment arising out of unreasonable delay in performing the contract, if the delay is caused by acts or omissions of the contracting agency or persons acting therefor, is against public policy and is void and unenforceable.

      (2) Subsection (1) of this section is not intended to render void any contract provision that:

      (a) Requires notice of any delay;

      (b) Provides for arbitration or other procedures for settlement of contract disputes; or

      (c) Provides for reasonable liquidated damages.