ORS 701.312: Additional grounds for placing contractor on probation.
Where this section sits in the code
- 17 - Occupations
- 52. Occupations and Professions
- Chapter 701 — Construction Contractors and Contracts
Notwithstanding the conditions specified for probation in ORS 701.102 (3), the Construction Contractors Board may place a contractor on probation as provided in ORS 701.102 (3) if the contractor offers to perform a home improvement, accepts a deposit of more than 50 percent of the total contract price and:
(1) Fails to perform diligently and in accordance with the contract specifications the home improvement for which the contractor received the deposit; or
(2) Fails to perform the home improvement for which the contractor received the deposit and fails to return the deposit within 10 days after a reasonable demand to return the deposit.
Collected 2026-09-03T23:50:17Z. Source file · JSON