62 Pa.C.S. § 3922: Payment of retainage to subcontractors.
Where this section sits in the code
- Title 62 - PROCUREMENT
- PART II GENERAL PROCUREMENT PROVISIONS
- CHAPTER 39 CONTRACTS FOR PUBLIC WORKS
- SUBCHAPTER C RETAINAGE
In the absence of sufficient reason, within 20 days of the receipt of payment by the contractor, the contractor shall pay all subcontractors with which it has contracted their earned share of the payment the contractor received.