SDCL § 44-9-26: Forfeiture of lien for failure to commence suit upon demand--Cancellation by register of deeds.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 44. LIENS
  2. CHAPTER 44-9. MECHANICS' AND MATERIALMEN'S LIENS

Upon written demand by the owner, the owner's agent, or contractor, served on any person holding a lien, requiring the person to commence suit to enforce the lien, the person shall commence suit within thirty days after such service or the lien is forfeited. The register of deeds shall cancel the lien of record, if the owner, the owner's agent, or contractor files no sooner than the fortieth day following service of the written demand:

(1) An affidavit stating that the person holding the lien has not commenced suit to enforce the lien within thirty days after the service of the written demand;

(2) A copy of the written demand that was served on the person holding the lien; and

(3) Proof of service on the person holding the lien.