SDCL § 49-34A-89: Withheld amounts paid at completion of project.
Where this section sits in the code
- TITLE 49. PUBLIC UTILITIES AND CARRIERS
- CHAPTER 49-34A. GAS AND ELECTRIC UTILITIES REGULATION
The amounts withheld by the department in accordance with § 49-34A-88 shall be retained until the project has been completed and the claimant has met all the conditions of §§ 49-34A-80 to 49-34A-92, inclusive, at which time all sums retained shall be paid to claimant.
Collected 2026-09-03T15:18:57Z. Source file · JSON