SDCL § 49-41B-15: Commission procedure following receipt of application for permit.
Where this section sits in the code
- TITLE 49. PUBLIC UTILITIES AND CARRIERS
- CHAPTER 49-41B. ENERGY CONVERSION AND TRANSMISSION FACILITIES
Within thirty days following receipt of an application for a permit, the commission shall:
(1) Schedule a public input meeting;
(2) Notify the applicant of the public input meeting; and
(3) Serve notice of the application and public input meeting upon the governing bodies of the counties and municipalities totally or partially within the area of the proposed facility.
Collected 2026-09-03T15:18:57Z. Source file · JSON