SDCL § 49-41B-15: Commission procedure following receipt of application for permit.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 49. PUBLIC UTILITIES AND CARRIERS
  2. CHAPTER 49-41B. ENERGY CONVERSION AND TRANSMISSION FACILITIES

Within thirty days following receipt of an application for a permit, the commission shall:

(1) Schedule a public input meeting;

(2) Notify the applicant of the public input meeting; and

(3) Serve notice of the application and public input meeting upon the governing bodies of the counties and municipalities totally or partially within the area of the proposed facility.