Tenn. Code Ann. § 13-18-119: Modification of project decision schedule

Read at publisher ↗
Where this section sits in the code
  1. TN Code
  2. Title 13
  3. Chapter 18

(a) At any time prior to the completion of the major energy project, the joint review team may: (1) Revise the special procedures for state or local agencies on the project decision schedule; (2) Add new special procedures for state or local agencies on the project decision schedule; (3) Revise any deadline on the project decision schedule; or (4) Add any new deadline on the project decision schedule. (b) No modification in the project decision schedule shall be allowed unless the team determines that: (1) Such modification would further the purposes of this chapter; (2) Continued adherence to the schedule would be impractical or would not be in the public interest; (3) In the case of a request for a modification by an agency, that the agency has exercised due diligence in attempting to comply with the schedule; (4) In the case of a request for a modification by an applicant, that the applicant has exercised due diligence in attempting to comply with the schedule; and (5) Except as provided by this section, such modification is consistent with § 13-18-114 and is published in a newspaper of general circulation. Acts 1981, ch. 131, § 19.

(a) At any time prior to the completion of the major energy project, the joint review team may: (1) Revise the special procedures for state or local agencies on the project decision schedule; (2) Add new special procedures for state or local agencies on the project decision schedule; (3) Revise any deadline on the project decision schedule; or (4) Add any new deadline on the project decision schedule.

(1) Revise the special procedures for state or local agencies on the project decision schedule;

(2) Add new special procedures for state or local agencies on the project decision schedule;

(3) Revise any deadline on the project decision schedule; or

(4) Add any new deadline on the project decision schedule.

(b) No modification in the project decision schedule shall be allowed unless the team determines that: (1) Such modification would further the purposes of this chapter; (2) Continued adherence to the schedule would be impractical or would not be in the public interest; (3) In the case of a request for a modification by an agency, that the agency has exercised due diligence in attempting to comply with the schedule; (4) In the case of a request for a modification by an applicant, that the applicant has exercised due diligence in attempting to comply with the schedule; and (5) Except as provided by this section, such modification is consistent with § 13-18-114 and is published in a newspaper of general circulation.

(1) Such modification would further the purposes of this chapter;

(2) Continued adherence to the schedule would be impractical or would not be in the public interest;

(3) In the case of a request for a modification by an agency, that the agency has exercised due diligence in attempting to comply with the schedule;

(4) In the case of a request for a modification by an applicant, that the applicant has exercised due diligence in attempting to comply with the schedule; and

(5) Except as provided by this section, such modification is consistent with § 13-18-114 and is published in a newspaper of general circulation.