Tenn. Code Ann. § 66-34-204: Payment of retainage by owner
Where this section sits in the code
- TN Code
- Title 66
- Chapter 34
When an owner: (1) Has received a use and/or occupancy permit for an improvement from a governmental agency lawfully issuing such permit; (2) Has received a certificate of substantial completion from an architect or engineer charged with supervision of the construction of an improvement; or (3) Begins to use or could have begun to use an improvement; the owner shall, after any such event and pursuant to the terms of the written contract, pay to the prime contractor all retainage the owner may have withheld pursuant to the written contract, except any sum which the owner may reasonably withhold in accordance with the written contract between the owner and the prime contractor; the retainage must be paid within ninety (90) days after the date of the occurrence of an event included in subdivision (1), (2) or (3). Amended by 2020 Tenn. Acts, ch. 749, s 21, eff. 7/1/2020. Acts 1991, ch. 45, § 1; 2007 , ch. 201, § 5.
When an owner:
(1) Has received a use and/or occupancy permit for an improvement from a governmental agency lawfully issuing such permit;
(2) Has received a certificate of substantial completion from an architect or engineer charged with supervision of the construction of an improvement; or
(3) Begins to use or could have begun to use an improvement; the owner shall, after any such event and pursuant to the terms of the written contract, pay to the prime contractor all retainage the owner may have withheld pursuant to the written contract, except any sum which the owner may reasonably withhold in accordance with the written contract between the owner and the prime contractor; the retainage must be paid within ninety (90) days after the date of the occurrence of an event included in subdivision (1), (2) or (3).
the owner shall, after any such event and pursuant to the terms of the written contract, pay to the prime contractor all retainage the owner may have withheld pursuant to the written contract, except any sum which the owner may reasonably withhold in accordance with the written contract between the owner and the prime contractor; the retainage must be paid within ninety (90) days after the date of the occurrence of an event included in subdivision (1), (2) or (3).