Tex. Property Code § 53.232: TO WHOM NOTICE GIVEN; MANNER.
Where this section sits in the code
- PROPERTY CODE
- TITLE 5. EXEMPT PROPERTY AND LIENS
- SUBTITLE B. LIENS
- CHAPTER 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN
- SUBCHAPTER J. LIEN ON MONEY DUE PUBLIC WORKS CONTRACTOR
The lien claimant must send written notice of his claim by certified mail to:
(1) the officials of the state, county, town, or municipality whose duty it is to pay the contractor; and
(2) the contractor at the contractor's last known business or residence address.
Acts 1983, 68th Leg., p. 3554, ch. 576, Sec. 1, eff. Jan. 1, 1984.
Amended by:
Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 30, eff. January 1, 2022.