Tex. Property Code § 53.234: TIME FOR NOTICE.

Read at publisher ↗
Where this section sits in the code
  1. PROPERTY CODE
  2. TITLE 5. EXEMPT PROPERTY AND LIENS
  3. SUBTITLE B. LIENS
  4. CHAPTER 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN
  5. SUBCHAPTER J. LIEN ON MONEY DUE PUBLIC WORKS CONTRACTOR

The lien claimant must give notice not later than the 15th day of the second month following the month in which the labor was performed or the material furnished.

Acts 1983, 68th Leg., p. 3555, ch. 576, Sec. 1, eff. Jan. 1, 1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 36, eff. Sept. 1, 1989.

Amended by:

Acts 2009, 81st Leg., R.S., Ch. 1304 (H.B. 2515), Sec. 3, eff. September 1, 2009.