Tex. Utilities Code § 39.053: COST RECOVERY ADJUSTMENTS.
Where this section sits in the code
- UTILITIES CODE
- TITLE 2. PUBLIC UTILITY REGULATORY ACT
- SUBTITLE B. ELECTRIC UTILITIES
- CHAPTER 39. RESTRUCTURING OF ELECTRIC UTILITY INDUSTRY
- SUBCHAPTER B. TRANSITION TO COMPETITIVE RETAIL ELECTRIC MARKET
This subchapter does not limit or alter the ability of an electric utility during the freeze period to revise its fuel factor or to reconcile fuel expenses and to either refund fuel overcollections or surcharge fuel undercollections to customers, as authorized by its tariffs and Sections 36.203 and 36.205.
Added by Acts 1999, 76th Leg., ch. 405, Sec. 39, eff. Sept. 1, 1999.