20VAC5-304-30: Minimum guidelines for data input and modeling assumptions

Read at publisher ↗
Where this section sits in the code
  1. Title 20. Public Utilities And Telecommunications
  2. Agency 5. State Corporation Commission
  3. Chapter 304. Rules Governing Cost/Benefit Measures Required for Demand-Side Management Programs

Minimum guidelines to provide direction to electric and natural gas utilities in developing applications for approval of DSM programs are as follows:

1. That the assumptions used in developing projected input data and the models used in the integrated resource planning process should be identified and well-documented. Utility-specific data should be used whenever possible (e.g., unit performance data, end-use load research data, market research data, etc.). In cases where utility-specific data are not available, the assumptions must be clearly defined;

2. That historic data, if available, should be assessed in developing projected data. Significant departures from historic trends should be explained;

3. That each projected data series should represent the Company's most current forecast;

4. That computer modeling techniques should be used in the development of an integrated resource plan;

5. That estimates of the capital and O&M (operation and maintenance) costs of supply-side options should include realistic projections of the costs of compliance with all promulgated environmental regulations or enacted legislation from which environmental regulations will be promulgated;

6. That each assumption and/or projected data series should be consistent with all other assumptions and/or projections. Consistency of data should be maintained between all models used within the integrated resource planning process; and

7. That alternative projections to determine sensitivity to input assumptions should be developed. These alternative projections should be used to perform cost/benefit analysis.

Waiver of strict adherence to these guidelines for small utilities or those in unusual circumstances may be granted by order of the Commission.