20VAC5-309-140: Excavator's responsibilities to avoid damage, dislocating or disturbances of utility lines

Read at publisher ↗
Where this section sits in the code
  1. Title 20. Public Utilities And Telecommunications
  2. Agency 5. State Corporation Commission
  3. Chapter 309. Rules for Enforcement of the Underground Utility Damage Prevention Act
  4. Part V. Supplemental Rules, Etc.

Any person excavating around underground utility lines shall take all reasonable steps to protect such utility lines. These steps shall include, but are not limited to, the following:

1. The excavator shall plan the excavation in such a manner to avoid damage to, and minimize interference with, underground utility lines in and near the construction area;

2. The excavator shall expose the underground utility line to its extremities by hand digging within the excavation area when excavation is expected to come within two feet of the marked location of the underground utility line;

3. The excavator shall not utilize mechanized equipment within two feet of the extremities of all exposed utility lines;

4. The excavator shall maintain a reasonable clearance, to include the width of the utility line, if known, plus 24 inches, between the marked or staked location of an underground utility line and the cutting edge or point of any mechanized equipment, considering the known limit of control of the cutting edge or point to avoid damage to the utility line; and

5. The excavator shall provide proper support for underground utility lines during excavation activities. During backfill operations, the excavator shall use the same or similar backfill material that was originally around the utility line, ensure there is proper compaction around the utility line, protect all tracer wires, and protect or replace warning tapes.