20VAC5-314-90: Commissioning tests
Where this section sits in the code
- Title 20. Public Utilities And Telecommunications
- Agency 5. State Corporation Commission
- Chapter 314. Regulations Governing Interconnection of Small Electrical Generators and Storage
Commissioning tests of the IC's installed equipment shall be performed pursuant to applicable codes and standards, including IEEE 1547.1, Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems, 2005. The utility shall be given at least five business days written notice, or notice as otherwise mutually agreed to in writing by the parties, of the tests to be performed, and the utility shall be allowed to witness the commissioning tests. The utility shall not be compensated by the IC for witnessing commissioning tests.