4VAC25-130-816.100: Contemporaneous reclamation
Where this section sits in the code
- Title 4. Conservation And Natural Resources
- Agency 25. Department of Energy
- Chapter 130. Coal Surface Mining Reclamation Regulations
- Part 816. Permanent Program Performance Standards—Surface Mining Activities
(a) General. Reclamation efforts, including but not limited to backfilling, grading, topsoil replacement, and revegetation, on all land that is disturbed by surface mining activities shall occur as contemporaneously as practicable with mining operations, except when such mining operations are conducted in accordance with a variance for concurrent surface and underground mining activities issued under 4VAC25-130-785.18.
(b) Timing of backfilling and grading.
(1) Contour mining. Rough backfilling and grading shall follow coal removal by not more than 60 days or 1,500 linear feet. The division may grant additional time for rough backfilling and grading if the permittee can demonstrate, through a detailed written analysis under 4VAC25-130-780.18(b)(3), that additional time is necessary.
(2) Open pit mining with thin overburden. Rough backfilling and grading shall occur in accordance with the time schedule approved by the division, on the basis of the materials submitted under 4VAC25-130-780.18(b)(3), which shall specifically establish in stated increments the period between removal of coal and completion of backfilling and grading.
(3) Area strip mining. Rough backfilling and grading shall be completed within 180 days following coal removal and shall not be more than four spoil ridges behind the pit being worked, the spoil from the active pit being considered the first ridge. The division may grant additional time for rough backfilling and grading if the permittee can demonstrate, through a detailed written analysis under 4VAC25-130-780.18(b)(3), that additional time is necessary.