9VAC25-875-300: Plan review requirements
Where this section sits in the code
- Title 9. Environment
- Agency 25. State Water Control Board
- Chapter 875. Virginia Erosion and Stormwater Management Regulation
- Part III. Virginia Erosion and Sediment Control Program
- Article 3. Programs Operated by a VESCP Authority
A. The VESCP authority shall review erosion and sediment control plans prepared in accordance with 9VAC25-875-550 that detail the criteria, techniques, and methods as defined in 9VAC25-875-560. Activities not required to comply with VESCL are defined in 9VAC25-875-280.
B. When the VESCP authority determines that the plan meets the minimum criteria, techniques, and methods as defined in 9VAC25-875-560, the VESCP authority shall review erosion and sediment control plans submitted and grant written approval within 60 days of the receipt of the plan.
C. When the VESCP authority determines a plan is inadequate, written notice stating the specific reasons for disapproval shall be communicated to the applicant within 45 days. The notice shall specify the modifications, terms, and conditions that are necessary for approval of the plan. If no action is taken by the VESCP authority within 45 days, the plan shall be deemed approved and the proposed activity authorized. The VESCP authority shall act on any erosion and sediment control plan that has been previously deemed inadequate within 45 days after receipt of a revised plan if deemed adequate.
D. For sites requiring coverage under the General VPDES Permit for Discharges of Stormwater from Construction Activities, the VESCP authority shall obtain evidence of such permit coverage from the department's online reporting system prior to issuing a land-disturbance approval.
E. The person responsible for carrying out the plan shall provide to the VESCP authority the name of an individual holding a certificate who will be in charge of and responsible for carrying out the land-disturbing activity. However, the VESCP authority may waive the Responsible Land Disturber Certificate requirement for an agreement in lieu of a plan in accordance with § 62.1-44.15.55 of the Code of Virginia.
F. The VESCP authority may require approval of an erosion and sediment control plan for any land identified as an erosion impact area in accordance with § 62.1-44.15.55 of the Code of Virginia.