9VAC5-50-260: Standard for stationary sources
Where this section sits in the code
- Title 9. Environment
- Agency 5. State Air Pollution Control Board
- Chapter 50. New and Modified Stationary Sources
- Part II. Emission Standards
- Article 4. Standards of Performance for Stationary Sources (Rule 5-4)
A. No owner or other person shall cause or permit to be discharged into the atmosphere from any affected facility any emissions in excess of emissions limitations representing best available control technology, as reflected in any term or condition that may be placed upon the minor NSR permit approval for the facility.
B. A new stationary source shall apply best available control technology for each regulated pollutant for which there would be an uncontrolled emission rate equal to or greater than the levels in 9VAC5-80-1105 C. For a new stationary source, a permit may be issued pursuant to Article 6 (9VAC5-80-1100 et seq.) of Part II of 9VAC5-80 (Permits for Stationary Sources) containing such terms and conditions as may be necessary to implement a best available control technology determination for any regulated air pollutant that may be emitted from any affected emissions unit.
C. A project shall apply best available control technology for each regulated pollutant for which there would be an increase in the uncontrolled emission rate equal to or greater than the levels in 9VAC5-80-1105 D. This requirement applies to each affected emissions unit in the project. For a project, a permit may be issued pursuant to Article 6 (9VAC5-80-1100 et seq.) of Part II of 9VAC5-80 (Permits for Stationary Sources) containing such terms and conditions as may be necessary to implement a best available control technology determination for any regulated air pollutant emitted, or that may be emitted, from any affected emissions unit.
D. For the phased construction of new stationary sources or projects, the BACT determination shall be reviewed and modified, as appropriate, at the latest reasonable time which occurs no later than 18 months prior to commencement of construction of each independent phase of the new stationary source or project. At such time, the owner of the applicable stationary source or project may be required to demonstrate the adequacy of any previous BACT determination for the affected emissions units.