9VAC5-520-210: Reporting requirements

Read at publisher ↗
Where this section sits in the code
  1. Title 9. Environment
  2. Agency 5. State Air Pollution Control Board
  3. Chapter 520. Biomass Energy Generator General Permit for a Pilot Test Facility
  4. Part IV. General Permit Terms and Conditions

A. The permittee shall comply with the reporting requirements in this section. Any document (including reports) required by a permit term or condition to be submitted to the department shall contain a document certification signed by a responsible official that meets the requirements of 9VAC5-20-230.

B. The permittee shall furnish written notification to the department of the following dates relative to the requirements of 9VAC5-520-180:

1. The actual date on which construction or installation of any biomass pilot test facility commenced, postmarked within 30 days after that date;

2. The anticipated startup date of the biomass pilot test facility, postmarked not more than 60 days nor less than 30 days prior to such date;

3. The actual startup date of the biomass pilot test facility postmarked within 15 days after that date;

4. The test protocol, postmarked at least 30 days prior to the date that testing commences; and

5. The test results, no later than 45 days after test completion of the stack tests and visible emissions evaluation.