9VAC5-540-160: Monitoring requirements
Where this section sits in the code
- Title 9. Environment
- Agency 5. State Air Pollution Control Board
- Chapter 540. Emergency Generator General Permit
- Part IV. General Permit Terms and Conditions
A. The owner shall install and use a nonresettable hour metering device to monitor the operating hours for each affected unit, calculated monthly as the sum of each consecutive 12-month period.
B. Each monitoring device shall be installed, maintained, calibrated, and operated in accordance with approved procedures, which shall include, as a minimum, the manufacturer's written requirements or recommendations.
C. The hour meter used to continuously measure the hours of operation for each affected unit shall be observed by the owner with a frequency of not less than once per month. The owner shall keep a log of the observations from the hour meter.
Collected 2026-09-14T04:48:50Z. Source file · JSON