W. Va. Code § 5-22B-13: Amendments to construction management at-risk contract after acceptance.

Read at publisher ↗
Where this section sits in the code
  1. CHAPTER 5. GENERAL POWERS AND AUTHORITY OF THE GOVERNOR, SECRETARY OF STATE AND ATTORNEY GENERAL; BOARD OF PUBLIC WORKS; MISCELLANEOUS AGENCIES, COMMISSIONS, OFFICES, PROGRAMS, ETC.
  2. ARTICLE 22B. GOVERNMENT CONSTRUCTION MANAGEMENT AT-RISK CONTRACTS.

A construction management at-risk contract may be conditioned upon later refinements in scope and price and may permit the state and/or its subdivisions in agreement with the construction manager to make changes in the project without invalidating the contract. Later refinements to a contract pursuant to the provisions of this section shall not exceed the scope of the project statement contained in the request for proposals.