10 CFR 40.33: Issuance of a license for a uranium enrichment facility.
Where this section sits in the code
- Title 10—Energy
- CHAPTER I—NUCLEAR REGULATORY COMMISSION
- PART 40—DOMESTIC LICENSING OF SOURCE MATERIAL
(a) The Commission will hold a hearing pursuant to 10 CFR part 2, subparts A, G, and I, on each application with regard to the licensing of the construction and operation of a uranium enrichment facility. The Commission will publish public notice of the hearing in the Federal Register at least 30 days before the hearing.
(b) A license for a uranium enrichment facility may not be issued before the hearing is completed and a decision issued on the application.
Collected 2026-08-27T02:24:09Z. Source file · JSON