10 CFR 50.23: Construction permits.
Where this section sits in the code
- Title 10—Energy
- CHAPTER I—NUCLEAR REGULATORY COMMISSION
- PART 50—DOMESTIC LICENSING OF PRODUCTION AND UTILIZATION FACILITIES
A construction permit for the construction of a production or utilization facility will be issued before the issuance of a license if the application is otherwise acceptable, and will be converted upon completion of the facility and Commission action, into a license as provided in § 50.56. However, if a combined license for a nuclear power reactor is issued under part 52 of this chapter, the construction permit and operating license are deemed to be combined in a single license. A construction permit for the alteration of a production or utilization facility will be issued before the issuance of an amendment of a license, if the application for amendment is otherwise acceptable, as provided in § 50.92.
Collected 2026-08-27T02:24:09Z. Source file · JSON