10 CFR 52.133: Relationship to other subparts.
Where this section sits in the code
- Title 10—Energy
- CHAPTER I—NUCLEAR REGULATORY COMMISSION
- PART 52—LICENSES, CERTIFICATIONS, AND APPROVALS FOR NUCLEAR POWER PLANTS
- Subpart E—Standard Design Approvals
(a) This subpart applies to a person that requests a standard design approval from the NRC staff separately from an application for a construction permit filed under 10 CFR part 50 or a combined license filed under subpart C of this part. An applicant for a construction permit or combined license may reference a standard design approval.
(b) Subpart B of this part governs the certification by rulemaking of the design of a nuclear power plant. Subpart B may be used independently of the provisions in this subpart.
(c) Subpart F of this part governs the issuance of licenses to manufacture nuclear power reactors to be installed and operated at sites not identified in the manufacturing license application. Subpart F of this part may be used independently of the provisions in this subpart.
Collected 2026-08-27T02:24:09Z. Source file · JSON