10 CFR 52.173: Duration of manufacturing license.
Where this section sits in the code
- Title 10—Energy
- CHAPTER I—NUCLEAR REGULATORY COMMISSION
- PART 52—LICENSES, CERTIFICATIONS, AND APPROVALS FOR NUCLEAR POWER PLANTS
- Subpart F—Manufacturing Licenses
A manufacturing license issued under this subpart may be valid for not less than 5, nor more than 15 years from the date of issuance. A holder of a manufacturing license may not initiate the manufacture of a reactor less than 3 years before the expiration of the license even though a timely application for renewal has been docketed with the NRC. Upon expiration of the manufacturing license, the manufacture of any uncompleted reactors must cease unless a timely application for renewal has been docketed with the NRC.
Collected 2026-08-27T02:24:09Z. Source file · JSON