10 CFR 52.33: Duration of renewal.

Read at publisher ↗
Where this section sits in the code
  1. Title 10—Energy
  2. CHAPTER I—NUCLEAR REGULATORY COMMISSION
  3. PART 52—LICENSES, CERTIFICATIONS, AND APPROVALS FOR NUCLEAR POWER PLANTS
  4. Subpart A—Early Site Permits

Each renewal of an early site permit may be for not less than 10, nor more than 20 years, plus any remaining years on the early site permit then in effect before renewal.