10 CFR 53.1336: Finality of construction permits.

Read at publisher ↗
Where this section sits in the code
  1. Title 10—Energy
  2. CHAPTER I—NUCLEAR REGULATORY COMMISSION
  3. PART 53—RISK-INFORMED, TECHNOLOGY-INCLUSIVE REGULATORY FRAMEWORK FOR COMMERCIAL NUCLEAR PLANTS
  4. Subpart H—Licenses, Certifications, and Approvals

Notwithstanding any provision in § 53.1590, a CP constitutes an authorization to proceed with construction but does not constitute Commission approval of the safety of any design feature or specification unless the applicant specifically requests such approval and such approval is incorporated in the permit. The applicant, at its option, may request such approvals in the CP or by amendment to the CP. If approved by the NRC and included in the permit, the NRC will consider modifications to the approved design features or specifications in accordance with § 53.1590.

Collected 2026-08-27T02:24:09Z. Source file · JSON

Browse this collection