10 CFR 950.34: Final claim determination.

Read at publisher ↗
Where this section sits in the code
  1. Title 10—Energy
  2. CHAPTER III—DEPARTMENT OF ENERGY
  3. PART 950—STANDBY SUPPORT FOR CERTAIN NUCLEAR PLANT DELAYS
  4. Subpart D—Dispute Resolution Process

(a) If the parties reach a Final Claim Determination through mediation, or Summary Binding Decision as set forth in this subpart, the Final Claim Determination is a final settlement of the issue, made by the sponsor and the Program Administrator.

(b) The parties agree that no appeal shall be taken or further review sought and that the Final Claim Determination is final, conclusive, non-appealable, and may not be set aside, except for fraud.