18 CFR 12.30: Applicability.

Read at publisher ↗
Where this section sits in the code
  1. Title 18—Conservation of Power and Water Resources
  2. CHAPTER I—FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
  3. SUBCHAPTER B—REGULATIONS UNDER THE FEDERAL POWER ACT
  4. PART 12—SAFETY OF WATER POWER PROJECTS AND PROJECT WORKS
  5. Subpart D—Review, Inspection, and Assessment by Independent Consultant

This subpart D applies to any licensed project development that:

(a) Has a dam

(1) That is more than 32.8 feet (10 meters) in height above streambed, as defined in § 12.31(c); or

(2) With an impoundment gross storage capacity of more than 2,000 acre-feet (2.5 million cubic meters), as defined in § 12.31(d);

(b) Has a project work (dam or water conveyance) or any portion thereof that has a high hazard potential, as defined in § 12.3(b)(13)(i); or

(c) Is determined by the Regional Engineer or other authorized Commission representative to require inspection by an independent consultant under this subpart D.