18 CFR 154.306: Cash working capital.
Where this section sits in the code
- Title 18—Conservation of Power and Water Resources
- CHAPTER I—FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
- SUBCHAPTER E—REGULATIONS UNDER NATURAL GAS ACT
- PART 154—RATE SCHEDULES AND TARIFFS
- Subpart D—Material To Be Filed With Changes
A natural gas company that files a tariff change under this part may not receive a cash working capital adjustment to its rate base unless the company or other participant in a rate proceeding under this part demonstrates, with a fully developed and reliable lead-lag study, a net revenue receipt lag or a net expense payment lag (revenue lead). Any demonstrated net revenue receipt lag will be credited to rate base; and, any demonstrated net expense payment lag will be deducted from rate base.