18 CFR 4.400: Applicability and purpose.

Read at publisher ↗
Where this section sits in the code
  1. Title 18—Conservation of Power and Water Resources
  2. CHAPTER I—FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
  3. SUBCHAPTER B—REGULATIONS UNDER THE FEDERAL POWER ACT
  4. PART 4—LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT COSTS
  5. Subpart N—Notice of Intent To Construct Qualifying Conduit Hydropower Facilities

This part implements section 30(a) of the Federal Power Act, as amended, and provides procedures for obtaining a determination from the Commission that the facility to be constructed is a qualifying conduit hydropower facility, as defined in § 4.30(b)(26), and thus, is not required to be licensed under Part I of the FPA.

Collected 2026-08-27T02:24:34Z. Source file · JSON