18 CFR 4.5: Time for filing protest.
Where this section sits in the code
- Title 18—Conservation of Power and Water Resources
- CHAPTER I—FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
- SUBCHAPTER B—REGULATIONS UNDER THE FEDERAL POWER ACT
- PART 4—LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT COSTS
- Subpart A—Determination of Cost of Projects Constructed Under License
Thirty days after service thereof will be allowed to such licensee within which to file a protest to such reports. If no protest is filed within the time allowed, the Commission will issue such order as may be appropriate. If a protest is filed, a public hearing will be ordered in accordance with subpart E of part 385 of this chapter.
Collected 2026-08-27T02:24:34Z. Source file · JSON