Upon issuance of a Commission order that notes a finding or findings, or proposed remedy or remedies, or both, in any combination, with which the audited person has disagreed, the audited person may: Acquiesce in the findings and/or proposed remedies by not timely responding to the Commission order, in which case the Commission may issue an order approving them or taking other action; or challenge the finding or findings and/or any proposed remedies, with which it disagreed by timely notifying the Commission in writing that it requests Commission review by means of a shortened procedure or, if there are material facts in dispute which require cross-examination, a trial-type hearing.
Collected 2026-08-27T02:24:34Z. Source file · JSON