2 CFR 1500.9: Revision of budget and program plans.
Where this section sits in the code
- Title 2—Federal Financial Assistance
- Subtitle B—Federal Agency Regulations for Grants and Agreements
- CHAPTER XV—ENVIRONMENTAL PROTECTION AGENCY
- PART 1500—UNIFORM ADMINISTRATIVE REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS
- Subpart D—Post Federal Award Requirements.
Pre-award Costs. EPA award recipients may incur allowable project costs 90 calendar days before the Federal awarding agency makes the Federal award. Expenses more than 90 calendar days pre-award require prior approval of EPA. All costs incurred before EPA makes the award are at the recipient's risk. EPA is under no obligation to reimburse such costs if for any reason the recipient does not receive a Federal award or if the Federal award is less than anticipated and inadequate to cover such costs.