2 CFR 910.354: Payment.
Where this section sits in the code
- Title 2—Federal Financial Assistance
- Subtitle B—Federal Agency Regulations for Grants and Agreements
- CHAPTER IX—DEPARTMENT OF ENERGY
- PART 910—UNIFORM ADMINISTRATIVE REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS
- Subpart D—Post Award Federal Requirements for For-Profit Entities
(a) For-Profit Recipients are an exception to 2 CFR 200.305(b)(1) which requires that non-Federal entities be paid in advance as long as certain conditions are met.
(b) For For-Profit Recipients who are paid directly by DOE, reimbursement is the preferred method of payment. Under the reimbursement method of payment, the Federal awarding agency must reimburse the non-Federal entity for its actual cash disbursements. When the reimbursement method is used, the Federal awarding agency must make payment within 30 calendar days after receipt of the billing, unless the Federal awarding agency reasonably believes the request to be improper.
Collected 2026-08-27T02:23:42Z. Source file · JSON