  1. Title 23—Highways
  2. CHAPTER I—FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION
  3. SUBCHAPTER G—ENGINEERING AND TRAFFIC OPERATIONS
  4. PART 636—DESIGN-BUILD CONTRACTING
  5. Subpart B—Selection Procedures, Award Criteria

You should consider using two-phase selection procedures for all design-build projects. However, if you do not believe two-phase selection procedures are appropriate for your project (based on the criteria in § 636.202), you may use a single phase selection procedure or the modified-design-build contracting method. The following procedures are available:

Selection procedure Criteria for using a selection procedure Award criteria options

(a) Two-Phase Selection Procedures (RFQ followed by RFP) § 636.202 Lowest price, Adjusted low-bid (price per quality point), meets criteria/low bid, weighted criteria process, fixed price/best design, best value.

(b) Single Phase (RFP) Project not meeting the criteria in § 636.202 All of the award criteria in item (a) of this table.

(c) Modified Design-Build (may be one or two phases) Any project Lowest price technically acceptable.