25 CFR 162.512: How long may the term of a WEEL run?

Read at publisher ↗
Where this section sits in the code
  1. Title 25—Indians
  2. CHAPTER I—BUREAU OF INDIAN AFFAIRS, DEPARTMENT OF THE INTERIOR
  3. SUBCHAPTER H—LAND AND WATER
  4. PART 162—LEASES AND PERMITS
  5. Subpart E—Wind and Solar Resource Leases

(a) A WEEL must provide for a definite term, state if there is an option to renew and if so, provide for a definite term for the renewal period. WEELs are for project evaluation purposes, and therefore may have:

(1) An initial term that is no longer than 3 years; and

(2) One renewal period not to exceed 3 years.

(b) The exercise of the option to renew must be in writing and the WEEL must specify:

(1) The time and manner in which the option must be exercised or is automatically effective;

(2) That confirmation of the renewal will be submitted to us, unless the WEEL provides for automatic renewal; and

(3) Additional consideration, if any, that will be due upon the exercise of the option to renew or the start of the renewal term.